Email Subject:
SCHEDULE UPDATE - Marion Pavement Improvements

Formatted HTML message

The Marion Department of Public Works, through the Contractor P.J. Keating Company, will begin reclamation and structure adjustment work for roadway improvements on Monday, October 28, 2024 on the following roadways: 

Allen Street (Front Street to Converse Road)

Lewis Street (Front Street to Water Street)

Pleasant Street (Converse Road to No. 3 Pleasant Street)

Cove Street (Cul de sac ONLY)

Zora Road (Converse Road to Front Street)

Hermitage Road (Route 6 to Cemetery / Private Road)

Installation of permanent pavement will follow during the week of November 4, 2024. Completion of all work is subject to change due to weather conditions. 

Please do not park any vehicles along the roadway during the construction period. Although the roadway will remain open to residents, motorists can expect delays while traveling through the construction area and should seek alternate routes. Every effort will be made to minimize inconvenience to residents and motorists. Your patience and cooperation are greatly appreciated. Please contact the Marion Department of Public Works should you have any questions or concerns: 508 748-3540. Thank you. 

Plain text message

The Marion Department of Public Works, through the Contractor P.J. Keating Company, will begin reclamation and structure adjustment work for roadway improvements on Monday, October 28, 2024 on the following roadways:

Allen Street (Front Street to Converse Road)

Lewis Street (Front Street to Water Street)

Pleasant Street (Converse Road to No. 3 Pleasant Street)

Cove Street (Cul de sac ONLY)

Zora Road (Converse Road to Front Street)

Hermitage Road (Route 6 to Cemetery / Private Road)

Installation of permanent pavement will follow during the week of November 4, 2024. Completion of all work is subject to change due to weather conditions.

Please do not park any vehicles along the roadway during the construction period. Although the roadway will remain open to residents, motorists can expect delays while traveling through the construction area and should seek alternate routes. Every effort will be made to minimize inconvenience to residents and motorists. Your patience and cooperation are greatly appreciated. Please contact the Marion Department of Public Works should you have any questions or concerns: 508 748-3540. Thank you.

SMS message

Pavement improvements have been rescheduled to begin on 10/28/24. Please see the Town of Marion website for details. Thank you.